Taking shape

Photo Album: 
Category: 

The last of the concrete foundation for the stage structure at the future Rainy Lake Square was poured yesterday, with backfilling to start next week. The stage structure was shipped this week and will be built upon arrival. Meanwhile, the entry canopy gabion walls are being completed and a large tower is being installed at the front of the site, while additional rock features are being installed in the plant beds in preparation for planting. The tree surrounds are complete, along with the foundations for the seating areas. The water system also is complete and being tested, with the bottle-filling station installed.