On a moonlit night—and using the lights from trucks, cell phones and back hoes—the crews from NST contracting from Thunder Bay, George Armstrong Co. Ltd. in Fort Frances and the general contractor, Bay City Construction, finished the single pour for the curbs and installation of the catch basins on the north side of the 300 block of Second Street East on Tuesday night. The south side curbing was expected to be completed yesterday, with the sidewalk installation to follow. The general contractor expects that Pioneer Construction will begin paving the street on Oct. 22.