Nearing completion

Photo Album: 
Category: 

Paving on the final section of the King’s Highway project should take place in the latter half of next week. The contractor is awaiting water sample results for the newly-installed watermain. If they come back clear, they’ll complete the final four watermain tie-ins, then install the geogrid, place granular materials at the watermain tie-in locations, and pave the road. The concrete island at the intersection of First Street West and King’s Highway also needs to be poured.