Murray Bullied of W.J. Bowman Ltd. drew a line for a co-worker to focus on while surveying the future site of Abitibi-Consolidateds biomass boiler Thursday afternoon in anticipation of site excavation starting on Monday, June 4. The $84.3 million projects foundation will be built over the summer, with the construction of the steel framework of the bio-mass boiler building to get underway in September, in anticipation of the boiler parts arriving next March (there will be no winter construction on the site). This will be followed by an intense period of construction of the boiler, with a completion date of October, 2008.